1224.08   CONFORMITY TO AN APPROVED SITE PLAN.
   (a)   Property, which is the subject of site plan approval, must be developed in strict compliance with the approved site plan, inclusive of any amendments, which have received the approval of the Planning Commission.
   (b)   Approval of the site plan is valid for a period of one-year. If a building permit has not been obtained and on-site development commenced within one-year, the site plan approval is void and a new application for site plan approval is required and new approval obtained before any construction or grading is commenced on the site. An extension request may be considered up to one additional year by the Planning Department.
(Ord. 2023-01. Passed 2-7-23.)