(A) The Zoning Administrator may grant an interim use permit for temporary storage of equipment in any zoning district in conjunction with highway construction or a similar public purpose.
(B) Such operation may include a bituminous plant, ready mix plant, contractor’s yard and similar uses.
(1) The use shall comply with all applicable federal, state and county rules, regulations and ordinances.
(2) All equipment and temporary buildings shall meet the setbacks of the underlying zoning district.
(3) The interim use permit shall contain a commencement and a termination date and any other conditions deemed necessary and proper to protect the surrounding properties.
(4) Any excavation of materials shall meet the standards of § 5.04 (Stormwater Management and Sediment and Erosion Control), where applicable.
(Ord. 97, passed 7-21-2009)