§ 153.03 AREA PLAN COMMISSION APPROVAL REQUIRED PRIOR TO PUBLIC WORKS CONSTRUCTION.
   (A)   Prior to the commencement of any public works program listed below in any unincorporated area written approval must be obtained from the County Area Plan Commission.
      (1)   In order to secure such approval the engineer, surveyor, consulting engineer, or the owner shall submit to the Area Planning Commission complete plans and specifications for the construction of:
         (a)   Any public water system.
         (b)   Any sanitary storm sewer system.
         (c)   Any gas distribution system.
         (d)   Any street or highway system.
      (2)   In any unincorporated area in which the construction of the above is contemplated and by this construction it is necessary to connect to or extend any existing or proposed system lying outside the corporate limits of all towns and cities, the Clerk- Treasurer of the town or city must file the above construction plans with the Area Plan Commission.
(BC Ord. passed 9-6-66)
   (B)   The Clerk-Treasurer of all towns and cities now participating in the County Master Development Plan are hereby required to furnish the Area Plan Commission with a complete copy of all plans for the establishment or extension of any and all public utilities within such participating town or city upon final approval thereof by the governing unit of such participating town or city.