§ 153.44  DECONSTRUCTION.
   (A)    The following shall apply to abandoned manufactured homes, whether completely intact or partially deconstructed:
      (1)   The contractor shall attempt to remove any recyclable materials from the abandoned manufactured home prior to demolition. Recyclable materials may include but are not limited to: metal, glass, wood, plastics, and thermostats containing mercury switches.
      (2)   The contractor shall deconstruct the home in a manner to minimize airborne debris.
      (3)   The demolition debris shall be contained on-site in a manner that would not cause any adverse effects or injury to adjoining properties.
      (4)   All materials must be delivered to a certified landfill or recycling center.
   (B)   The deconstruction contractor will bring the landfill receipt(s) to the Public Works Department upon completion. The deconstruction process shall be carried out in a manner as to cause the least amount of disturbance or least amount of damage to the subject property. Any adverse effects or injury to adjoining properties caused by the contractor's failure to contain the demolition debris shall be the sole responsibility of the contractor and not the county.
(Ord. passed 9-14-2009; Ord. passed 6-7-2021)