§ 15-221 SAME; EXCESS COSTS PRORATED.
   In the event the new electrical system plan prepared and submitted by the developer and approved by the Superintendent requires installation of wire larger in size than is necessary to serve the new electrical system area, then the city shall pay the difference between the cost of the wire required to be installed and the cost of wire of the size necessary to serve the area, but the difference in cost may be charged by the city to subsequently developed new electrical system areas that are served by the wire.
(Ord. 1225, passed 5-2-1995)