§ 154.26 CONSTRUCTION, DEMOLITION, AND RENOVATION.
   (A)   The following work within the municipal boundaries of the city shall require a city building permit and an Institutional Controls Program (ICP) permit from Panhandle Health District No. 1 (hereinafter referred to as “District”):
      (1)   Construction of new buildings and additions to existing buildings, which require excavation;
      (2)   Demolition of buildings, which require excavation;
      (3)   Renovation of buildings which would result in excavation; and
      (4)   Such other things that would be required by other rules of the state involving the Institutional Controls Program (ICP).
   (B)   Applications for Institutional Controls Program permits from the District shall be obtained from the Health District office, Kellogg, Idaho, and shall be issued (or the need for a permit waived) by the District prior to the issuance of the city building permit. Upon issuance of both permits, each shall be filed with the City Clerk.
   (C)   Applications for an Institutional Controls Program permit shall be made to the District within 30 days of submitting an application to the city for a building permit. The city building permit and the Institutional Controls Program permit, when required, must be approved and issued prior to the applicant commencing work.
   (D)   In the event a city building permit is not required, an Institutional Controls Program permit shall nonetheless be required for excavations, except as exempted, for the purpose of providing for contaminated soil management.
(Prior Code, § 11-2-2) (Ord. 2008-01, passed 2-13-2008)