§ 51.26 APPLICATION.
   A customer desiring to interconnect renewable generation facilities with the utility's grid, for the purpose of offsetting the customer's electric load, shall complete an interconnection application and submit it to the utility for review. After receiving the application, the utility shall conduct such further inspection of the renewable generation facilities as it deems necessary, and shall approve or deny the application. If the application is denied, the utility shall provide a written response to the customer explaining why the application was denied. The utility is hereby authorized to charge a reasonable application fee to offset the costs of reviewing the application, inspecting the renewable generation facilities, and otherwise ensuring compliance with this subchapter.
(Ord. 2022-1, passed 1-24-2022)