111.02 STIPULATED DAMAGES IN CONTRACTS.
   (a)   There is hereby established as stipulated damages in contracts entered into between the Village and successful bidders who perform work and supply service and materials to the Village the following sums as stipulated on a per diem basis for the failure of such contractors to timely complete particular contracts pursuant to the terms thereof, to wit:


Original Contract Amount
Amount of Liquidated Damages to be Deducted for each Calendar Day of Overrun in Time


From More than


To & Including
$0
$15,000
$30.00
15,000
25,000
60.00
25,000
50,000
100.00
50,000
100,000
150.00
100,000
250,000
200.00
500,000
1,000,000
300.00
1,000,000
2,000,000
400.00
2,000,000
5,000,000
600.00
5,000,000
10,000,000
800.00
over 10,000,000
950.00
   (b)   The stipulated damages required by this section shall not apply to a contractor whose completion of a contract with the Village has been delayed by an Act of God, a civil disturbance or a labor strike.
   (c)   Council may, by an affirmative vote of the members present, modify or waive such portions of the stipulated damages as they deem reasonable.
(Ord. 01-2004. Passed 1-7-04.)