No land, new building, or structure shall be occupied or used, in whole or in part, and no change in the use of an existing building or structure, or any part thereof, shall be permitted, until a Certificate of Zoning Compliance has been applied for and issued by the Zoning Administrator. A Certificate of Zoning Compliance shall also be required prior to the use or occupancy of any building or land, if Section 1125.03, Zoning Certificate Required, requires said land or building to receive a Zoning Certificate.
(a) Certificate of Zoning Compliance shall be applied for and issued as follows:
(1) Occupancy of a Building. A Certificate of Zoning Compliance shall be required before a building that has been constructed, or an existing building that has been altered, moved, changed in use, changed in tenancy, or changed as to off-street parking requirements may be occupied. A Certificate of Zoning Compliance shall only be issued after the completion of the erection or alteration, or change in use of the building and the building is found, upon inspection by the Zoning Administrator, to conform with the provisions of this Zoning Code and any other applicable Village regulations, policies, and specifications.
(2) Occupancy of Land. A Certificate of Zoning Compliance shall be required before occupancy of the land or where use of the land has been changed to a use different from the prior use, except for agricultural uses. A Certificate of Zoning Compliance shall be issued when it is determined, upon inspection, that the use conforms with the provisions of this Zoning Code.
(3) Change in Use of Non-conforming Building or Use. A Certificate of Zoning Compliance shall be required whenever a nonconforming building, structure, or land is changed to another nonconforming use, and shall not be issued until the Board of Zoning Appeals has approved the change in accordance with the provisions of Chapter 1135, Nonconforming Uses, Lots, and Structures.
(b) An application for Certificate of Zoning Compliance shall include, in addition to the plans required for the Zoning Certificate, accurate information as to the size, location, drawings and description of the lot, the dimensions of yards and setbacks, and the use of land.
(c) The use and/or development of a building or land shall be inspected by the Zoning Administrator upon application for a Certificate of Zoning Compliance, by the owner or his agent, to determine whether such use conforms to all provisions of this Zoning Code and the approved final site plan as applicable, or if it is a lawfully existing nonconforming use.
(d) Action by Zoning Administrator. The Zoning Administrator shall evaluate the application and approve or deny it within fifteen (15) days from the date the completed application was submitted. In evaluating the application, the Zoning Administrator may consult with any department, agency, public body, official, company, or individual necessary to determine whether the application complies with the regulations of this Zoning Code. Following the Zoning Administrator's review, the Zoning Administrator shall:
(1) Approve. The Zoning Administrator shall issue a Certificate Zoning of Compliance upon finding that the building, structure or use, as proposed, complies with the provisions of this Zoning Code, if the maintenance and performance guarantees have been provided, as applicable.
(2) Denial. If it is determined by the Zoning Administrator that the proposed building, structure or use would violate one or more provisions of this Zoning Code, then the Certificate of Zoning Compliance shall not be issued. Upon disapproval of any application, the Zoning Administrator shall notify the applicant in writing of the reasons for disapproval.
(3) Temporary Certificate of Zoning Compliance. Pending the issuance of a permanent Certificate of Zoning Compliance, a temporary certificate may be issued, to be valid for a period not to exceed (6) six months from its date, pending the completion of any required improvements, provided a performance guarantee or bond has been provided to the Village from a banking institution of sufficient amount to cover the estimated cost of materials and labor and in a form acceptable to the Law Director.
(e) Certification. The Certificate of Zoning Compliance shall document that the building or proposed use of land or building conforms to the provisions of this Zoning Code. The applicant shall not seek a building occupancy permit from Lake County until the County has received a valid Certificate of Occupancy from the Village of Waite Hill.
(f) Records. A record of all applications and certificates issued shall be kept on file in the office of the Zoning Administrator, and copies shall be furnished, upon request, to any person requesting such records.
(Ord. 2011-14. Passed 4-9-12.)