§ 91.14 INSPECTIONS.
   (A)   Notice of completion. When the work under any permit hereunder is completed, the permittee shall furnish a completion certificate in accordance with PUC Rules.
      (1)   Unless waived by the city, a person designated by the right-of-way user as a responsible employee shall sign a completion certificate showing the completion date for the work performed, identifying the installer and designer of record, and certifying that work was completed according to the requirements of the city.
      (2)   If necessary, due to approved changes for the work as projected when the permit was applied for, the permittee shall submit “as built” drawings or maps within six months of completing the work, showing any deviations from the plan that are greater than plus or minus two feet.
      (3)   The city shall respond within 30 days of receipt of the completion certificate. Failure to approve or disapprove the permittee’s performance within 30 days is deemed to be approval by the city.
   (B)   Site inspection. The permittee shall make the work site available to the Public Works Director and to all others as authorized by law for inspection of utility main connections and entirety of project at all reasonable times during the execution of and upon completion of the work.
   (C)   Authority of Public Works Director.
      (1)   At the time of inspection the Public Works Director may order the immediate cessation of any work which poses a serious threat to the life, health, safety, or well-being of the public.
      (2)   (a)   The Public Works Director may issue an order to the permittee for any work which does not conform to the terms of the permit or other applicable standards, conditions, or codes.
         (b)   The order shall state that failure to correct the violation will be cause for revocation of the permit. Within ten days after issuance of the order, the permittee shall present proof to the Public Works Director that the violation has been corrected.
         (c)   If such proof has not been presented within the required time, the Public Works Director may revoke the permit pursuant to § 91.46.
(2006 Code, § 14.60) (Ord. 196, Third Series, passed 4-14-2015)