929.02 RATES, FEES AND CHARGES FOR SEWER SYSTEM.
RULES AND REGULATIONS
   The Rules and Regulations as set forth in current Sewer Tariff No. 6 shall remain
unchanged.
SCHEDULE I
APPLICABILITY
Applicable to entire territory served
AVAILABILITY OF SERVICE
Available for domestic, commercial and industrial sewer service
RATES
 
First
5,000 gallons used per month
$9.10 per 1,000 gallons
Next
15,000 gallons used per month
$6.50 per 1,000 gallons
Over
20,000 gallons used per month
$4.55 per 1,000 gallons
MINIMUM CHARGE
Each customer shall pay a minimum charge of $18.20 per month
(Equivalent to 2,000 gallons of water usage)
UNMETERED RATE (Customers with non-metered water supply)   $40.95
Equivalent of 4,500 gallons of water usage
DELAYED PAYMENT PENALTY
The above schedule is net. On all accounts not paid in full when due, ten percent will be added to the net current amount unpaid. This delayed payment penalty is not interest and is to be collected only once for each bill where it is appropriate.
TAP FEE
The following charges are to be made whenever the utility installs a new tap to serve an applicant.
A tap fee of $100.00 will be charged to customers applying for service before construction is completed adjacent to the customer's premises in connection with a certificate proceeding before the Commission. This pre-construction tap fee will be invalid after the completion of construction adjacent to the applicant's premises that is associated with a certificate proceeding.
A tap fee of $350.00 will be charged to all customers who apply for service outside of a certificate proceeding before the Commission for each new tap to the system.
Whenever a road bore is necessary, cost will be increased depending upon amount of footage, cost of materials and labor. Sewer Department will go to property line or 50 feet, whichever is less.
WATER DISCONNECT-RECONNECT-ADMINISTRATIVE FEES
Whenever water service has been disconnected for non-payment of sewer bills, a disconnection fee of $25.00 shall be charged; or in the event the delinquent sewer bill is collected in the field, an administrative fee of $25.00 shall be charged.
Whenever water service which has previously been disconnected or otherwise withheld for non-payment of a sewer bill, is reconnected, a reconnection fee of $25.00 shall be charged.
RETURNED CHECK CHARGE
A service charge of $25.00 will be imposed upon any customer whose check for payment of charges is returned by the bank for any reason.
LEAK ADJUSTMENT
$3.50 per 1,000 gallons is to be used when a bill reflects unusual consumption which can be attributed to eligible leakage on customer's side of the meter. This rate shall be applied to all such consumption above the customer's historical average usage.
SECURITY DEPOSIT
All new applicants for residential or other sewer service may be required to deposit (i) a minimum of fifty dollars ($50.00) or (ii) two-twelfths (2/12) of the annual estimated charge for sewer service, whichever is greater.
All new applicants for residential or other combined water and sewer service may be required to deposit (i) a minimum of one hundred dollars ($100.00), or (ii) two-twelfths (2/12) of the annual estimated charge for each service, whichever is greater.
SCHEDULE II
Schedule II as set forth in current Sewer Tariff No. 6 shall remain unchanged.
SCHEDULE III
Schedule III as set forth in current Sewer Tariff No.6 shall remain unchanged.
SCHEDULE IV
Schedule IV as set forth in current Sewer Tariff No.6 shall remain unchanged.
SCHEDULE V
Schedule V as set forth in current Sewer Tariff No.6 shall remain unchanged.
(Ord. 08-17. Passed 10-26-17.)