The supervision of all tests and the field inspection of materials and workmanship shall be performed by the City Engineer, or his representative. This inspection shall be continuous during the time of construction and the City shall be reimbursed for the cost of such inspection by the subdivider.
The contractor for the subdivider is required to notify the City Engineer as to the date on which the work will start and when a City inspector will be required. It is necessary that the contractor give the Engineer at least twenty-four hours notice in each instance where an inspector is to be provided, except when the inspector will be needed on a Monday, in which case the notification must be received on the preceding Friday. If an inspector is not available due to the contractor not complying with the foregoing twenty-four hours notice, no construction work on the affected project will be permitted.
Any defects noted by the City Engineer shall be corrected as directed by the City Engineer before any further construction work is done.
(Ord. 850. Passed 7-1-63; Ord. 74-42. Passed 5-6-74.)