(A) All electrical wiring and equipment for which a permit is required by this code shall be subject to inspection and approval of the Building Commissioner. No electrical wiring or parts thereof shall be covered or concealed without authorization to do so by the Building Commissioner or Electrical Inspector.
(B) Notice shall be given that the work is ready for inspection at least 24 hours in advance and the work shall be inspected within 2 work days from receipt of notice. Official notices of approval or disapproval will be placed in a conspicuous place by the inspector.
(C) All roughing in for electrical wiring shall be inspected and approved before being concealed. Final inspection shall be made and approved before the work is placed in service. Prior to final inspection, the installer shall provide permanent circuit identification by means of a permanent circuit schedule in or at the distribution panel. If the work is found to be incomplete or not in conformity with this code, the necessary corrections shall be made and the work then resubmitted for final inspection.
(1981 Code, § 152.31) (Ord. 6572-93, passed 12-13-1993)