(A) Inspections are required for site, footer and foundation work. No work is to be started prior to having a site inspection, when applicable. Other inspections will be scheduled at the discretion of the Building Commissioner or Building Inspector.
(B) Notice shall be given that the work is ready for inspection at least 24 hours in advance and the work shall be inspected within 2 work days from receipt of notice. Official notices of approval or disapproval will be placed in a conspicuous place by the inspector.
(1981 Code, § 152.26) (Ord. 6572-93, passed 12-13-1993)