1224.08 IMPROVEMENT INSTALLATIONS.
   (a)   Easements and Inspections. No improvement shall be installed until the required approval has been secured and until easements and rights of way have been recorded. No work shall be performed without Village inspection, which inspection shall be paid for by the owner.
   (b)   Grading. The rights of way and easements shall be graded to a cross- section approximately within six inches of the finished grade as approved by the Village Engineer before the various underground utilities are installed.
   (c)   Sewers and Water Mains. The installation of sanitary sewers, storm sewers, water mains and appurtenances thereto shall be completed and tested according to the approved plans and Village standards.
   (d)   Temporary Roadways. If the weather or other conditions make it impossible to install the pavement immediately after the underground improvements are completed, a temporary roadway may be installed. The temporary roadway shall be a minimum of eight inches thick and twenty feet wide and shall be composed of slag or similar material.
   (e)   Pavement. The pavement shall be installed and tested according to the approved plans and Village standards.
   (f)   Street Signs. Village standard street signs shall be furnished and installed by the Village at the owner's expense after the pavement is completed. These signs shall be placed at locations designated by the Village.
   (g)   Sidewalks. Sidewalks shall be installed according to the approved plans and Village standards.
(Ord. 84-5-4. Passed 5-1-84.)