1020.05 STREET EXCAVATIONS; STEEL PLATE REQUIRED.
   In connection with the construction of utilities within any dedicated street or any street proposed to be dedicated, the owner and contractor shall plan the work so as to present a minimum of inconvenience to the normal flow of traffic. Where any trenches cross the traveled portion of a street that is kept open to traffic, the contractor shall furnish and install at his own cost a steel plate satisfactory to the Village Engineer to insure the flow of normal traffic. All trench backfill for utilities that cross any existing or proposed right-of-way where proposed or existing drives, walks or pavement is to be installed should be backfilled with low strength mortar (LSM) as approved by the Village Engineer.
(Ord. 65-3-5. Passed 4-6-65; Ord. 2017-3-15. Passed 3-7-17.)