(A) Plan required. Prior to any Design Review Board approval for a building in the Arterial Business District or enlargement of an existing Arterial Business District by change of zone district boundaries the Planning and Environmental Commission shall adopt a general circulation and access plan for the proposed zone district.
(B) Plan content. The Administrator shall establish the submittal requirements for a general circulation and access plan application. A complete list of the submittal requirements shall be maintained by the Administrator and filed in the Department of Community Development. Certain submittal requirements may be waived and/or modified by the Administrator and/or the reviewing body if it is demonstrated by the applicant that the information and materials required are not relevant to the proposed development or applicable to the planning documents that comprise the Vail Comprehensive Plan. The Administrator and/or the reviewing body may require the submission of additional plans, drawings, specifications, samples and other materials if deemed necessary to properly evaluate the proposal.
(C) Plan used as guide. The general circulation and access plan shall be used as a guide for the subsequent development of sites and the design and location of buildings and grounds within the zone district. All plans subsequently approved by the Design Review Board in accordance with Chapter 11 of this title shall substantially conform to the plan adopted by the Planning and Environmental Commission.
(D) Amendments to plan. The general circulation and access plan can be amended by the Planning and Environmental Commission at a public hearing.
(E) Prior approval required. Before a building permit is issued on any building, design guidelines for streets and parking lot lights, pavement treatment and benches, must be submitted and approved by the Department of Community Development.
(Ord. 5(1982) § 1; Ord. 5(2003) § 10; Ord. 29(2005) § 24)