§ 8-1-20 STORAGE OF EXCAVATED MATERIAL.
   Excavated materials shall be laid compactly along the side of the trench in a manner so as to cause as little inconvenience as possible to public travel. In order to expedite the flow of traffic or to abate a dirt or dust nuisance, Public Works may require the permittee to provide toe boards or bins, and if the excavated area is muddy and causes inconvenience to pedestrians, temporary walks shall be installed by the permittee as directed by Public Works.
(Ord. 7(1971) § 4(I); Ord. 43(1978) § 1; Ord. 7(2006) § 17)