(A) Conformance to environmental impact report. Upon approval of the project, applicable permits may be issued and the project may proceed, subject to such additional requirements, permits, or authorizations as may be required by this title and by other applicable ordinances or regulations of the town. No permits shall be issued and no authorizations shall be granted which would allow a project to proceed in the event that the Planning and Environmental Commission does not grant approval of the environmental impact report after review. No permits shall be issued and no authorizations shall be granted for any project which does not conform substantially to the description of the project contained in the environmental impact report.
(B) Exception. This section shall not apply to a project for which an environmental impact report is not required, as prescribed in § 12-12-3 of this chapter.
(Ord. 8(1973) § 16.504; Ord. 16(1978) § 2(b); Ord. 29(2005) § 31)