(a) The applicant or applicants shall apply in writing to the Planning Commission for a planned unit development permit, such application to be accompanied by all necessary, general and detailed plans for determinations.
(b) The Commission shall treat such application as an amendment, certifying its recommendations to Council.
(c) Council shall act in the same manner prescribed by law for amending this Zoning Ordinance.
(d) If a planned unit development is permitted, permits shall be issued according to such approval given by Council, and the approved development shall become a part of this Ordinance as would any other amendment.
(e) If after twenty-four months, no construction has been started and if within five years the development has not been completed, the area involved shall revert back to the original district.
(f) All duly approved planned unit development, shall be designated a "P.U.D." on the official Zoning Map.
(Ord. 113-9. Passed 1-17-94.)