§ 206-51.   General requirements.
   A.   No regulated activities within the Township shall commence until the Township Engineer approves a stormwater management operations and maintenance plan which describes how the permanent (e.g., postconstruction) stormwater management facilities will be properly operated and maintained.
   B.   The following items shall be included in the stormwater management operations and maintenance plan:
      (1)   Plan(s) of the project area, in a form that can be recorded at the Offices of the Recorder of Deeds of Montgomery County, submitted on twenty-four-inch-by-thirty-six-inch sheets. The contents of the maps(s) shall include, but not be limited to:
         (a)   Clear identification of the location and nature of all permanent stormwater management facilities.
         (b)   The location of the project site relative to watercourses, roads, municipal boundaries or other identifiable landmarks.
         (c)   Existing and final contours at intervals of two feet, or others as appropriate.
         (d)   Existing wetlands, floodplains, streams, lakes, ponds or other watercourses within the project site area.
         (e)   Other physical features, including flood hazard boundaries, sinkholes, existing drainage courses and areas of natural vegetation to be preserved.
         (f)   The locations of all existing utilities, sanitary sewers, and water lines within 100 feet of property lines of the project site.
         (g)   Proposed final changes to the land surface and vegetative cover, including the type and amount of impervious area that would be added, and the type, amount and depth of fill material to be placed.
         (h)   Proposed structures, roads, paved areas and buildings.
         (i)   A twenty-foot wide access easement to all stormwater management facilities for ingress to and egress from a public right-of-way.
      (2)   A description of how each permanent stormwater facility will be operated and maintained and the identity of the person(s) responsible for operations and maintenance,
      (3)   The name of the project site, the name and address of the owner of the property and the name of the individual or firm preparing the plan.
      (4)   A statement, signed by the landowner, acknowledging that the stormwater management facilities are fixtures that can be altered or removed only after approval by the Township.
      (5)   Legal document to be recorded that subjects the alteration or removal of stormwater management facilities to the approval of the Township.