[Added 7-14-1998 by Ord. No. 973; amended 5-13-2014 by Ord. No. 14-1289, § 8]
In accordance with Chapter 206, Stormwater Management, the following fees shall be charged:
A. Plan review.
(1) Sketch stormwater management plan for exempt activities pursuant to § 206-16: $125.
(2) Stormwater management plan for regulated activities pursuant to § 206-5: $500.
(3) Modified plan, resubmitted plan, or renewal of expired plan: $150.
(4) For the review of swales, berms and diversions, $225. [Added 5-13-2014 by Ord. No. 14-1289]
B. Stormwater management permit issuance: $25.
C. Inspection charges.
(1) Exempt activities. Inspection by the Township Engineer shall only occur if requested by the applicant or the Director of Code Enforcement.
(2) Regulated activities. Inspection by the Township Engineer will occur as needed in accordance with the plan approval by the Board of Commissioners or the Director of Code Enforcement.
(3) The inspection fees of the Township Engineer shall be billed to the permit applicant at the approved, standard hourly rate charged to the Township by the Township Engineer.
D. No permit to begin any work on the project shall be issued and no site work shall begin until the requisite plan review and permit fees have been paid. Inspection fees will be billed by the Township according to its standard schedule. The Township reserves the right to revoke any stormwater management permit for nonpayment of inspection fees.
E. Modification of plans. If it is determined that an existing stormwater management plan shall be modified, a new stormwater management permit shall not be issued until any additional review or permit fees have been paid by the applicant.
F. Renewal of expired plan. If an applicant requests the renewal of an expired plan, the application will not be approved nor a permit reissued until any additional review or fees have been paid by the applicant.