Project:_______________________________ By:_____________ Date: ______________
Location:______________________________ Checked_________ Date: ______________
Circle one:PresentDeveloped ________________________________________
Circle one:TCTC through subarea _______________________________
NOTES: Splice for as many as two segments per flow type can be used for each worksheet.
Include a map, schematic, or description of flow segments.
Sheet Flow (Applicable to TC only)Segment ID | ||||
1. Surface description (App. B, Table 8) | ||||
2. Manning's roughness coeff., “n” (App. B, T.8) | ||||
3. Flow length, L (total L 300 feet)ft. | ||||
4. Two-year, 24-hour rainfall, P2in. | ||||
5. Land slope, sft./ft. | ||||
6. Tt = {0.007 (nL) 0.8}/{P20.5 s0.4} Compute Tt..hr. |
Shallow Concentrated Flow Segment ID | ||||
7. Surface description (paved or unpaved) | ||||
8. Flow length, Lft. | ||||
9. Watercourse slope, sft./ft. | ||||
10. Average velocity, V (App. B, Table 8)ft./s | ||||
11. Tt=L/(3600V)Compute Tthr. |
Channel FlowSegment ID | ||||
12. Cross sectional flow area, aft.2 | ||||
13. Wetted perimeter, pw ft. | ||||
14. Hydraulic radius, r=a/pw Compute rft. | ||||
15. Channel slope, sft./ft. | ||||
16. Manning's roughness coeff., “n” | ||||
17. V=(1.49 r2/3 s1/2)/nCompute Vft./s | ||||
18. Flow length, Lft. | ||||
19. Tt=L/(3600V)Compute Tthr. | ||||
20. Watershed or subarea Tc or Tt (add Tt, steps 6, 11, 19)hr. | ||||