(a) The subdivider shall install a water system for the subdivision. A complete water main system shall be connected to a public water supply, plans for which are reviewed and approved by the City Manager and the Ohio Environmental Protection Agency. All water mains shall be a minimum of six inches in size. The plans for the complete installation showing size, location, depth, material and all connections thereto including fire hydrants, shall meet the requirements and receive the approval of the Ohio Environmental Protection Agency.
(b) Water supply improvements shall be completed in accordance with the plans and profiles prepared for the subdivider by a registered professional engineer and approved by the Municipal Engineer to meet the minimum requirements specified in Union’s “Waterworks General Concept Plan” and “Standard Specifications and Construction Drawings for Public Improvements”. Water supply improvements shall be carried out under Municipal supervision within the time fixed or agreed upon by the City Manager, and all inspection costs shall be paid for by the subdivider.
(c) Water lines serving cul-de-sacs that exceed 300 feet in length measured from the street centerline to the center point of the cul-de-sac shall be connected back into the water distribution system.
(Ord. 333. Passed 12-10-73.)