§ 51.015 APPLICATION.
   Any person, or corporation desiring public water service shall file an application/permit with the Township Clerk or Supervisor, containing the name and address of the applicant; a description of the land or premises to be serviced; the nature of the use anticipated for the water; the size of the water service connection pipes desired; the distance, if known, that the property is located from any existing public water main extension. After the initial connection fee (tap fee) is paid to the township, the township will have the water tap installed to the curb stop. Then it is the property owners’ responsibility to have the connection made between the curb stop and point of connection for water usage. A permit from the County Building and Zoning Department is required for the connection at point of service.
(Ord. passed 4-4-2017)