§ 13.3-3  GENERAL REQUIREMENTS: PC ZONE.
   The following requirements shall apply to all PC zoned areas.
   (A)   An application for a zone change to permit the establishment of a PC Zone shall include and be accompanied by a development plan for the entire property.
   (B)   An application for a zone change to establish a PC Zone must be for a parcel or parcels of land under control of the person or corporation proposing the development.
   (C)   The area contained within a proposed PC Zone shall not be less than ten acres.
   (D)   A conditional use permit may be required for any land use designation on the development plan.
   (E)   If ambiguity exists as to the specific dimensions or extent of any designated area on the development plan, the specific boundaries shall be set by the filing of a legal description and map of the parcel in question in conjunction with the filing of a conditional use permit, tentative subdivision or construction permits.
(Ord. 2012-04, passed 12-5-2012)