(a) Subdivision developers shall be responsible, where the main extension has been approved by the Utility, for the water service lateral installation costs from the main through the curb stop and box for the sewer lateral installation costs from the main to the property line.
(b) When the cost of a utility main extension is to be collected through assessment by the municipality, the actual average water lateral installation costs from the main through the curb stop and box, and the sewer installation costs from the main to the property line shall be included in the assessment of the appropriate properties.
(c) The initial water and sewer lateral(s), not installed as part of a subdivision development or an assessable utility extension, will be installed from the main through the curb stop and box (property line for sewer laterals) by the Utility, for which there will be made a charge as follows:
3/4-inch or 1-inch copper water service | $175 |
4-inch sewer service | $175 |
Larger sized services | Actual cost |
(Prior Code, § 9-1-10)