When an applicant installs sewer mains larger than eight inches as directed by the General Manager, the General Manager shall prepare a reimbursement agreement after the main has been installed and actual costs determined to be executed by the applicant and the president of the Board of Public Utilities pursuant to the provisions of Title 8, Chapter 8.64 of this code. The amount of oversize reimbursement shall be equal to the difference in cost between an eight-inch main and the actual size of main installed. Provided, however, when the General Manager determines that the installing applicant requires larger than an eight-inch main to serve the applicant’s whole property, the amount of oversize reimbursement shall be equal to the difference in cost between the size of main needed by the applicant to serve the applicant’s whole property and the actual size of main installed.
(1995 Code, § 7.20.1000) (Ord. 17-03, passed 3-21-2017; Ord. 15-02, passed 5-5-2015)