(A) Within 12 months after approval of the preliminary plan by the Borough Council, the developer or his or her agent shall submit a final plan and all required supplementary data to the Borough Secretary unless an extension of time is granted by the Borough Council. If an extension is not granted, failure to submit the final plan within 12 months will result in any plan submitted after 12 months being considered as a new preliminary plan.
(B) The final plan shall be submitted to the Borough Secretary no later than 28 days prior to a regularly scheduled meeting of the Borough Planning Commission.
(Ord. 1-2006, passed 5-8-2006)