§ 90.800.4 CONSTRUCTION INSPECTION CHECKLIST.
Construction Stage
Inspection Items
Subgrade
Street subgrade constructed to accurate grade and within specified tolerances.
Moisture condition of subgrade (+ 3% of optimum unless otherwise approved in writing).
Subgrade stability (Proof rolling required in addition to density tests. Proof- roll to be performed with rubber-tired construction vehicle weighing a minimum of 25 tons such as a fully loaded, tandem-axle dump truck unless otherwise approved in writing by City Engineer.).
Base Course
Base course constructed to accurate grade and within specified tolerance.
Surface texture uniform (no evidence of segregation).
Moisture condition of base course.
Base course stability (Proof rolling required in addition to density tests. Proof-roll to be performed with rubber-tired construction vehicle weighing a minimum of 25 tons such as a fully loaded, tandem-axle dump truck unless otherwise approved in writing by City Engineer.)
Curb and gutter
Curb and gutter alignment and grade accuracy.
Cross section in conformance with typical detail.
Concrete finish as specified. No toppings or thin patches permitted. No cracks or other defects.
Joint spacing accurate. Joint filler and sealer complete.
Where removal and replacement of curb and gutter is required, the replacement section shall extend from joint to joint or as directed by the City Engineer.
Surfacing
Grade and cross section accurate. Surfaces within prescribed tolerance.
Texture and finish uniform.
Joints straight and smooth. Joint filler and sealer completed. No cracks or openings at joints.
Finish pavement surface shall not be lower than the top of gutter.
 
(Ord. 2009-11-347, passed 11-3-09; Am. Ord. 2010-06-356, passed 6-1-10 ; Am. Ord. 2018-11-816, passed 11-6-18)