300.02 Discharging Procedures
   A.   Go to Central Operations Building to make log book entries, submit ticket.
   B.   Complete logbook columns 1-8.
   C.   Submit a completed CITY OF TOLEDO LIQUID SEPTIC HAULERS MANIFEST to the Plant operator.
   D.   The Plant operator will unlock the Septage discharge station and operate the odor control system as required.
   E.   Unload the waste in a proper manner.
   F.   Clean the building, pull hoses off to the side, and turn the water off.
   G.   Return to the Central Operations Building when finished discharging and initial column 8 in the log book to indicate that you have cleaned the Septic Discharge Building. See that the operator initials column 9 to acknowledge that the building was cleaned and locked.