§ 161.03 APPLICABILITY.
   (A)   The provisions of this chapter govern the construction of wind energy conversion systems (WECS) and substations that generate electricity to be sold to wholesale or retail markets, or that generate electricity for private use.
   (B)   No applicant shall construct, operate, or locate a wind energy conversion system (WECS) within the county after March 1, 2010 without having fully complied with the provisions of this chapter and the County Unified Zoning Ordinance.
   (C)   No final approval of construction for any wind energy conversion systems (WECS) or structure erected, altered or repaired after March 1, 2010 shall be granted unless such wind energy conversion systems (WECS) or structure was erected, altered or repaired in compliance with the provisions of this chapter.
(Ord. 2010-02-CM, passed 4-5-10; Am. Ord. 2010-24-CM, passed 2-21-11)