§ 50.25 INSPECTION TO DETERMINE COMPLIANCE.
   An inspection of the entire site shall be made by the Health Officer to determine compliance with approved plans and specifications before the earth- moving equipment is removed from the site. Any necessary corrective work shall be performed before the landfill project is accepted as completed. Arrangements shall be made for the repair of all cracked, eroded, and uneven areas in the final cover during the first two years following completion of the landfill.
(Ord. 76-19, passed 6-14-76)