(A) Major contributors shall make application for the proposed discharge on a form provided by the city. The permit application shall be supplemented by any plans, specifications, studies or other information considered pertinent by the Board.
(B) Major contributors shall pay an initial major contributor permit fee of $100 for connection to the sewage works.
(C) To establish a feasible surveillance schedule, the following class of major contributors are formed:
Class | Qualification | Minimum Surveillance Schedule |
A | Flow of 100,000 gallons per day or more per average workday | Quarterly |
B | Flow from 40,000 to 100,000 gallons per average workday or discharge with constituents or characteristics that result in a major contributor classification | Semiannually |
(D) The surveillance period will normally be for a period of seven consecutive days, but can be of longer or shorter duration at the discretion of the Board or Superintendent. In cases where the surveillance periods extend for a greater number of consecutive days than seven, the city shall have the prerogative of selecting the seven consecutive days of its choice for establishing rates and charges, as provided for in the sewer rate ordinance.
(Ord. 599, passed 12-3-1984; Am. Ord. 1130, passed 11-30-2017)