§ 155.152 RELEASE OF SECURITY.
   (A)   No portion of the road construction, maintenance, storm water and erosion control security will be released as the work progresses. The entire amount posted/deposited shall be retained until all work covered by the security is satisfactorily completed and approved by the County Engineer.
   (B)   Prior to the release of any bond or other adequate security for subdivision improvements, a letter of acceptance from the Township Highway Commissioner and/or the County Engineer shall be submitted to the Plat Officer. Additionally, a letter from the registered professional engineer in charge of construction of such improvements shall be required to certify that all improvements have been completed in accordance with the approved engineering plans and specifications on file in the County Community Development Department. Such certification shall cover all engineering aspects of the development, including, but not limited to, erosion control methods, roads, detention/retention, grading, filling, and any topographic changes or adjustments proposed.
   (C)   The developer shall have two years to complete all subdivision improvements after submittal of the good and sufficient bond or other adequate security or the county shall have the right to the good and sufficient bond or other adequate security for completion of the subdivision improvements.
(Res. LU-20-10, passed 11-18-2020)