(A) If a special use that has been granted is not implemented according to the plans as presented and approved within one year from the date of approval by the ZBA, such special use shall be rescinded by the Community Development Administrator.
(B) A special use about to expire may be extended for a year by application for renewal through written request of said special use to the Zoning Board of Appeals, only if there are no changes proposed from the initial approval. If changes are proposed aside from a request for extension the original application, the request shall be considered a new request and the application process shall be in accordance with the requirements of §§ 157.480 through 157.492.
(C) If a special use that has been granted and implemented, subsequently ceases operation for a period of six consecutive months, that special use shall be deemed terminated and shall not be reestablished except by following the process as required for the initial grant of such use.
(Prior Code, 7 TCC 1-25(l)) (Res. LU-23-02, passed 1-25-2023)