15.08.020: FEES IN GENERAL:
Section 107.3 of the 1977 uniform building code with respect to fees is hereby adopted and incorporated herein by reference. Section 107.3 of the 1977 uniform building code, as adopted herein, is hereby amended to read as follows:
When submittal documents are required by section 106.3.2 of the uniform building code, a plan review fee shall be paid at the time of submitting the submittal documents for review. Said plan review fee shall be as follows:
   1. Forty percent of the building permit for other R-3 and U occupancies; and
   2. Sixty-five percent of the building permit fee for all other occupancies.
EXCEPTIONS:
   1. When, in the opinion of the building official, plans can be reviewed under an established expedited procedure, the plan review fee for R-3 and U occupancies, including swimming pools and signs, shall not exceed $30.
   2. Plans which have been previously reviewed and placed in the city's plan card file in contemplation of future permit issuance shall be charged a plan review in an amount approved by the council. Such plans may be used for issuing new permits until a new edition of the building code is adopted by the state of Utah. In such case, the plans shall be resubmitted for review by the city. The cost for such review shall be as required for "additional plan review," with a minimum of two hours. Any such plans which are not used for a period of 18 months shall be resubmitted for a full plan review, with all required fees, if they are to be used again. Card file plans shall comply with administrative procedures established by the building official.
   The plan review fees specified in this subsection are separate fees from the permit fees specified in section 107.2 of the uniform building code and are in addition to the permit fees.
   When submittal documents are incomplete or changed so as to require additional plan review or when the project involves deferred submittal items as defined in section 106.3.4.2 of the uniform building code, an additional plan review fee shall be charged at the rate shown on the fee table.
   Charges for other services to be provided by the building department shall be based upon the hourly rates indicated in the building code and assessed according to the following:
   A. Renewal of expired permits where only final inspections are required, four hours;
   B. Reinspection, one hour;
   C. Inspection requested outside of normal working hours, minimum two hours;
   D. Review of new products or materials for acceptance, minimum four hours;
   E. Request for verification of conformance to code for existing buildings, minimum one hour.
   The building official may determine charges for other services provided for which fees are not indicated.
   (Ord. 02-01, 1-2-2002)