1459.046 AS-BUILT PLANS, COMPLETION CERTIFICATE, AND FINAL INSPECTIONS.
   (a)   The developer shall be responsible for providing as-built plans of all SWM BMPs included in the approved SWM site plan for activities involving proposed impervious surfaces 1,000 square feet or greater and for earth disturbances 5,000 square feet or greater. The as-built plans and all explanation of any discrepancies with the construction plans shall be submitted to the Borough within three months of the completion of construction of the SWM BMPs.
   (b)   As-built plans shall show the location and as-built conditions of all SWM BMP structures and include the following information: impervious surfaces included in the approved SWM site plan; topographic contours; and existing, proposed, and built impervious surfaces shown in the as-built drawings.
   (c)   The as-built submission shall include a certification of completion signed by a design professional verifying that all permanent SWM BMPs have been constructed according to the approved plans and specifications.
   (d)   The Borough will review the as-built submission for consistency with the approved SWM site plan as well as actual conditions at the project site. After receipt of the completion certification by the Borough, the Borough may conduct a final inspection.
(Ord. 1051. Passed 8-13-12.)