1459.037 PLAN SUBMISSION.
   The Borough shall require receipt of a complete SWM site plan, as specified in this chapter.
   (a)   Proof of application or documentation of required permit(s) or approvals for the programs listed below shall be part of the plan, if applicable:
      (1)   NPDES Permit for Stormwater Discharges from Construction Activities.
      (2)   PADEP permits as needed:
         A.   PADEP Joint Permit Application;
         B.   Chapter 105 (Dam Safety and Waterway Management); and
         C.   Chapter 106 (Floodplain Management).
      (3)   PennDOT Highway Occupancy Permit.
      (4)   Any other permit under applicable State or Federal regulations.
   (b)   The plan shall be coordinated with the State and Federal permit process and the municipal SALDO review process.
   (c)   For projects that require SALDO approval, the SWM site plan shall be submitted by the applicant as part of the preliminary plan submission where applicable for the regulated activity.
   (d)   For regulated activities that do not require SALDO approval, see Section 1459.015, General Requirements.
   (e)   Five copies of the SWM site plan shall be submitted by the applicant for review in accordance with established criteria and procedures:
      (1)   Two copies to the Borough accompanied by the requisite Borough review fee.
      (2)   Two copies to the County Conservation District.
      (3)   One copy to the Borough Engineer.
   (d)   Any submissions to the agencies listed above that are found to be incomplete shall not be accepted for review and shall be returned to the applicant with a notification in writing of the specific manner in which the submission is incomplete.
(Ord. 1051. Passed 8-13-12.)