§ 150.677 TERMS AND DURATION OF APPROVAL.
   (A)   Conditional use approval shall authorize a particular conditional use on the specific parcel for which it was approved. Approval of a conditional use, pursuant to this Article, shall be valid only for the use and the operation of such use as specified when granted by the Planning Commission. The breach of any condition, safeguard, or requirement shall constitute a violation of this Zoning Code.
   (B)   A conditional use permit issued pursuant to this Article shall be valid only to the applicant to whom the permit is issued, unless the new owner agrees to all conditions, safeguards and requirements in the conditional use permit and a transfer of such permit is approved by the Zoning Administrator.
   (C)   The conditional use permit shall become null and void within a six-month period after the date of approval, unless:
      (1)   In the case of new construction, work upon the structure shall have begun above the foundation walls;
      (2)   In the case of occupancy of land, the use has commenced;
      (3)   As otherwise specifically approved by the Planning Commission at the time the conditional use approval is granted; or
      (4)   The Zoning Administrator grants an extension for good cause shown, upon the request of the applicant.
   (D)   A conditional use permit may be considered abandoned and void if, for any reason, the conditional use is not conducted for more than six months.
(Ord. 2023-03, passed 2-27-2023)