§ 150.675 DECISION.
   (A)   The Planning Commission shall take action upon such application within 45 days after the date of receiving said application; failure to act within such period shall be deemed approval, unless an extension of this time is agreed to by the applicant.
      (1)   Approval. The Planning Commission may approve or approve with conditions the application for a conditional use permit.
      (2)   Denial. The Planning Commission may deny the application for a conditional use permit. If the Planning Commission denies the application, the application process ends. Disapproval of the application for a conditional use permit shall include a statement of the reasons for the denial.
      (3)   Failure of the Planning Commission to act within the time, or an extended period as may be agreed upon, shall at the election of the applicant be deemed a denial of the application.
   (B)   All conditions imposed upon any conditional use approval, with the exception of conditions made applicable to such approval by the terms of this Zoning Code, shall be set forth expressly in the resolution granting the conditional use permit.
(Ord. 2023-03, passed 2-27-2023)