(A) All plumbing installation or alteration performed after the issuance of a permit shall be inspected by the Plumbing Inspector or his or her legally authorized representative at the following stages:
(1) Upon completion of groundwork, but prior to covering;
(2) Upon completion of rough in, but prior to covering; and
(3) Following completion, but prior to use.
(B) Responsibility for notifying the Code Administrator that a specific stage of construction has been reached and that inspection is requested shall rest solely with the applicant.
(C) No new building or structure shall be occupied or used unless it has passed each inspection and a certificate of occupancy has been issued.
(D) All fees, as set forth in § 150.004 of this chapter, for any inspection required by this chapter shall be paid, in advance, prior to the issuance of a permit, at the Swansea Government Center, 1400 North Illinois Street, Swansea, IL.
(Prior Code, § 15-508)