(A) All electrical installation or alteration performed after the issuance of a permit shall be inspected by the Code Administrator or his or her legally authorized representative at the following stages:
(1) Upon installation of any temporary service;
(2) Upon completion of rough in, but prior to covering;
(3) Upon completion of permanent service; and
(4) Following completion, but prior to occupancy.
(B) Responsibility for notifying the Code Administrator that a specific stage of construction has been reached and an inspection is requested shall rest solely with the applicant.
(C) (1) No new building or structure shall be occupied or used unless it has passed each inspection and a certificate of occupancy has been issued.
(2) No new or remodeled electrical installations shall be connected with the electrical power supply lines until the same have received a final inspection and certificate of approval from the Code Administrator.
(D) All fees, as set forth in § 150.004 of this chapter, for any inspection required by this chapter shall be paid, in advance, prior to the issuance of a permit, at the Swansea Government Center, 1400 North Illinois Street, Swansea, IL.
(Prior Code, § 15-306)