§ 93.05 CLOSING STREETS; PRIVATE CONSTRUCTION.
   Any person or firm seeking the temporary occupation or the closure of all or part of any street, alley or sidewalk for any purpose in connection with the erection, removal, alteration or repair of any building or other structure shall first make application to the Superintendent of Public Works or his or her designated representative. The Superintendent of Public Works shall approve, with conditions if deemed necessary, or deny the application considering the duration of the closure, the practicality of the detour plan, the arrangements for appropriate detour and closure signage and the safety and convenience of the public. The Superintendent of Public Works shall give 48 hours’ notice to the Police and Fire Departments and the ambulance company of any scheduled street closure.
(Prior Code, § 6-305) (Ord. 1634, passed 12-19-2011)