Whenever possible, the building sewer shall be brought to the building at an elevation below the basement floor. The depth shall be sufficient to afford protection from the frost. All excavations required for the installation of a building sewer shall be open trench work unless otherwise approved by the Inspector. Pipe laying and backfill shall be performed in accordance with A.S.T.M. specifications (designation C12); except that, no backfill shall be in place until the work has been inspected and approved by the inspector or his or her representative.
(Prior Code, § 6-809)