§ 154.017-03 FLOODPLAIN DEVELOPMENT PERMIT, ZONING PERMIT, AND CERTIFICATION REQUIREMENTS.
   (A)   Floodplain development permit. The floodplain development permit shall include, but not be limited to:
      (1)   A description of the development to be permitted under the floodplain development permit;
      (2)   The special flood hazard area determination for the proposed development per available data specified in § 154.017-01;
      (3)   The regulatory flood protection elevation required for the reference level and all attendant utilities;
      (4)   The regulatory flood protection elevation required for the protection of all public utilities;
      (5)   All certification submittal requirements with timelines;
      (6)   A statement that no fill material shall encroach into the floodway or non-encroachment area of any watercourse, as applicable;
      (7)   The minimum opening requirements, if in Zone A, AO, AE or A1-30; and
      (8)   Limitations of below BFE enclosure uses (if applicable) (i.e., parking, building access and limited storage only).
      (9)   The Floodplain Administrator shall make as many inspections of the work pursuant to a floodplain development permit as may be necessary to ensure that the work is being done according to the provisions of this subchapter and the terms of the permit. In exercising this power, the Floodplain Administrator has a right upon presentation of proper credentials, to enter on any premises within the jurisdiction of the community at any reasonable hour for the purposes of inspection or other enforcement action.
   (B)   Issuance of zoning permits. A zoning permit, hereinafter referred to as the "floodplain development permit" shall be required in conformance with the provisions of this subchapter prior to the commencement of any development activities within special flood hazard areas as determined in § 154.017-01.
   (C)   Elevation certification requirements.
      (1)   An elevation certificate (FEMA Form 81-31) is required prior to the actual start of any new construction. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the elevation of the reference level, in relation to mean sea level. Elevation certification shall be prepared by, or under direct supervision of, a registered land surveyor or professional engineer and certified by same. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder prior to the beginning of construction. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit.
      (2)   An elevation certificate (FEMA Form 81-31) or flood-proofing certificate (FEMA Form 81-65) is required after the reference level is established. Within seven calendar days of establishment of the reference level elevation, it shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the elevation of the reference level in relation to mean sea level. Elevation certification shall be prepared by, or under the direct supervision of, a registered land surveyor or professional engineer and certified by same. Any work done within the seven-day calendar period and prior to submission of the certification shall be at the permit holder's risk. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to further work being permitted to proceed. Failure to submit the certification or failure to make required corrections shall be cause to issue a stop-work order for the project.
      (3)   A final as-built elevation certificate (FEMA Form 81-31) is required after construction is completed and prior to certificate of compliance/occupancy issuance. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of final as-built construction of the elevation of the reference level and all attendant utilities. Elevation certification shall be prepared by, or under the direct supervision of, a registered land surveyor or professional engineer and certified by same. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder immediately and prior to certificate of compliance/occupancy issuance. In some instances, another certification may be required to certify corrected as-built construction. Failure to submit the certification or failure to make required corrections shall be cause to withhold the issuance of a certificate of compliance/occupancy.
      (4)   Flood-proofing certificate. If non-residential flood-proofing is used to meet the regulatory flood protection elevation requirements, a flood-proofing certificate (FEMA Form 81-65) is required prior to the actual start of any new construction. It shall be the duty of the permit holder to submit to the Floodplain Administrator a certification of the flood-proofed design elevation of the reference level and all attendant utilities in relation to mean sea level. Flood-proofing certification shall be prepared by or under the direct supervision of a professional engineer or architect and certified by same. The Floodplain Administrator shall review the certificate data submitted. Deficiencies detected by such review shall be corrected by the permit holder prior to the beginning of construction. Failure to submit the certification or failure to make required corrections shall be cause to deny a floodplain development permit. Failure to construct in accordance with the certified design shall be cause to withhold the issuance of a certificate of compliance/occupancy.
      (5)   Engineered foundation certification. If a manufactured home is placed within Zone A, AO, AE or A1-30 and the elevation of the chassis is more than 36 inches in height above grade, an engineered foundation certification is required per § 154.017-07.
      (6)   Engineering report. If a watercourse is to be altered or relocated, a description of the extent of watercourse alteration or relocation; an engineering report on the effects of the proposed project on the flood-carrying capacity of the watercourse and the effects to properties located both upstream and downstream; and a map showing the location of the proposed watercourse alteration or relocation shall all be submitted by the permit applicant prior to issuance of a floodplain development permit.
      (7)   Certification exemptions. The following structures, if located within Zone A, AO, AE, or A1-30, are exempt from the elevation/flood-proofing certification requirements specified in divisions (A) and (B) above:
         (a)   Recreational vehicles meeting requirements of § 154.017-07;
         (b)   Temporary structures meeting requirements of § 154.017-07; and
         (c)   Accessory structures less than 150 square feet meeting requirements of § 154.017-07.
   (D)   Floodplain Administrator authority to revoke permits or stop work.
      (1)   The Floodplain Administrator may revoke and require the return of the floodplain development permit by notifying the permit holder in writing stating the reason(s) for the revocation. Permits shall be revoked for any substantial departure from the approved application, plans or specifications; for refusal or failure to comply with the requirements of state or local laws; or for false statements or misrepresentations made in securing the permit. Any floodplain development permit mistakenly issued in violation of an applicable state or local law may also be revoked. Whenever a building or part thereof is being constructed, reconstructed, altered, or repaired in violation of this subchapter, the Floodplain Administrator may order the work to be immediately stopped. The stop-work order shall be in writing and directed to the person doing the work. The stop-work order shall state the specific work to be stopped, the specific reason(s) for the stoppage, and the condition(s) under which the work may be resumed. Violation of a stop-work order constitutes a misdemeanor.
      (2)   The Floodplain Administrator may revoke and require the return of the floodplain development permit by notifying the permit holder in writing stating the reason(s) for the revocation. Permits shall be revoked for any substantial departure from the approved application, plans or specifications; for refusal or failure to comply with the requirements of state or local laws; or for false statements or misrepresentations made in securing the permit. Any floodplain development permit mistakenly issued in violation of an applicable state or local law may also be revoked.
(Ord. passed 4-17-2023)