§ 150.334 STANDARDS AND SPECIFICATIONS; GENERAL.
   (A)   The City Engineer shall inspect all land grading, drainage, detention and water quality controls to determine compliance with the released site plan.
   (B)   When construction of these facilities is complete, the design engineer shall submit a concurrence letter to the City Engineer stating that in the engineer's opinion, the project is in substantial conformance with the approved construction plans. A final inspection will then be performed by the City Engineer. If all applicable Code provisions and construction plan requirements are met, a Certificate of Occupancy will be released by the accountable official.
   (C)   Final acceptance of facilities by the city, or approval of Certificates of Occupancy shall not be issued until a water quality control inspection of the facility and certificate of compliance is completed by the city.