No sewer trench shall be filled or sewer pipe covered until the building sewer has been first inspected by the Director and other duly authorized employees of the city. Persons making sewer connections shall give at least 24 hours’ notice to the Director of the time when such service sewer shall be ready for inspection. The Director shall inspect such sewer within a reasonable time and if such service sewer is not properly laid or connected, the public works director shall order the same to be taken out and relaid.
(Ord. 30, passed 8-21-2008) Penalty, see § 53.999