(a) The Building Director and/or City Engineer or their designees shall inspect all buildings at the following periods of construction and such inspections shall condition the permit holders authority to proceed further:
(1) Installation of footers before they are poured.
(2) Completion of foundation including waterproofing.
(3) Completion of roughing-in the plumbing, electrical, wiring, gas piping, heating ducts or piping, or other similar service installations regulated by this Building Code.
(4) Completion of insulation.
(5) Before closing in all structural elements.
(6) Upon the final completion of the structure, and its systems.
(b) The Building Director or his designee may also inspect such building at any time as he may determine to be necessary or desirable.
(c) Before applying for a Certificate of Occupancy, the applicant shall request a grading inspection. The City Engineer shall verify, through inspection, the final rough grading conforms to the approved grading plan and specifications. This inspection shall be completed before an occupancy will be issued.
(Ord. 2021-08. Passed 1-11-21.)