65.24   SEPTIC CONSTRUCTION PERMIT TO BE ISSUED BY EH. 
Upon receipt and EH approval of the application, payment, site evaluation report (if applicable), easement documents (if required) and maintenance contract (if required), EH shall issue a permit using information obtained from the site evaluation report, soil survey, flood maps, permit application, and other pertinent information. EH may apply policy or variations of design, which have been approved or recommended by the BOH, the Professional Evaluator, EPA, IDNR, or the University Extension Engineering Specialists in efforts to enhance wastewater treatment or increase the system's longevity. The permit shall outline the basic construction design and minimum system size as defined in 567 IAC 69, along with any restrictive conditions or requirements. Mandatory system maintenance and monitoring requirements, easements, and other special conditions shall be stipulated on the permit.